Road Work Advisories

About Our Advisories

Online resources for up-to-date information about City of Eugene transportation system road construction. Read below for the weekly roadwork report (available April- November).


Current City of Eugene Roadwork Advisories

Updated June 24, 2022


Major road construction is scheduled for the week of June 27, weather permitting. Use caution in work zones and obey traffic control signage and flaggers. Links to additional project information can be found at www.eugene-or.gov/roadwork. For real-time traffic impacts, go to TripCheck.com or twitter.com/EugenePW.


City of Eugene


17th Ave, 19th Ave & Mill St Paving –Milling and Paving will occur Mill St. from 16th Ave. to 18th Ave. Expect road closures, no on-street parking and limited access. Vehicles should plan to use alternative routes or designated detours. Pedestrians should expect detours to be signed where sidewalks are disrupted. Use alternate routes when possible.


Catalina St, Chase St, Concord St, Echo Hollow Rd, Fuller Ave & Hawthorne Ave Paving – Manhole adjustments will be occurring throughout the project limits. Traffic will be directed around the location of work being performed with minimal impacts. Please be mindful of construction crews and give them safe distance to work as you pass by.


Amazon Pkwy from E 19th Ave to E 20th Ave – The west sidewalk on Amazon Pkwy from E 19th Ave to E 20th Ave will be closed through June 30. Expect one-lane closures with flaggers as required.


Coburg Road (Ferry Street Bridge to Willamette River Bridge) - Day work on the Willamette River Bridge will continue with cleaning and structural work under the bridge. There will be no impacts to the public.
 

Downtown Wayfinding Signs - The City will be installing wayfinding signs throughout the downtown corridor. Construction crews will be minimal, and their work will be behind the curb. Little to no traffic disruption is anticipated. Please be mindful of construction crews and give them safe distance to work as you pass by.


822 W. 18th Place – Asphalt repair projected to begin June 24.  Local residents should be alert for door hangers and no parking barricades as the road will be closed during the work.  Street will be accessible only to residents. Work is weather dependent.


4740 Royal Avenue, June 28 -   Flaggers on site; entrance to Albertsons store from N. Danebo Avenue will be closed for a day, working on the concrete bike path.


544 East 13th Avenue, June 29 - 13th Ave- Closed between Ferry and Patterson for asphalt work.


446 East13th Avenue, June 30 - Site detour around work zone between Mill St. and Ferry St. for asphalt work.


1958 Minda Drive, July 1 - Asphalt work, watch for signs. Low impact on traffic.

 

Jessen Dr, Clarey St & Robin Ave - Work is ongoing on Jessen Dr between Elizabeth St and Hwy 99, on N Clarey St between Bean St and Century Dr, and on Robin Ave between Taney St and Ruskin St. Work will be primarily on weekdays between 7 am and 6 pm and will include adjusting manholes in the roadway, landscaping repair, and some asphalt paving. Slurry sealing will begin on cul-de-sacs off of N Clarey Dr and will require closures during the day to allow the slurry to cure.  Affected homeowners have been notified by the contractor.  Drivers and cyclists should expect minor delays and be prepared to navigate localized lane closures around active work. Pedestrians should expect detours to be signed where sidewalks are disrupted. All users are encouraged to use alternative routes when possible. This project is expected to be completed no later than July 15.


Grand Cayman Dr (north of Barbados Dr) – Ongoing construction of Striker Field Park adjacent to Grand Cayman Dr will have limited impact on local traffic until the fall of 2022.  Please watch for the movement of workers, construction equipment and trucks.      


Harris Pkwy (in front of Autzen Stadium) – Work will take place on the east-bound lane of Harris Pkwy from June 14-17, including concrete work on curb, gutter, and sidewalk, and asphalt work for approximately 65 feet. Watch for the following signs: CREW WORKING, ROAD CLOSED AHEAD and TRANSITION LEFT.  Expect workers to detour traffic around the work zone. 


Peter DeFazio Bridge – The bridge will be closed for the entirety of the week as cleaning and painting operations continue. Pedestrians and cyclists are encouraged to use the Ferry Street Bridge as a detour, and signs will indicate the route. 


Silver Ln west of River Rd – Work is ongoing at North Eugene High School on the south side of Silver Ln through the summer to April 2023. Work includes pavement repair, walk, curb and gutter replacement. Potential flagging as required.  


Inlet Bottom Construction and Repairs – This project will clean and construct new catch basin/inlet bottoms in 212 structures throughout Eugene. Work will be occurring at multiple locations, with current focus at 27th Ave & Laurelwood and 36th Ave & Knob Hill. This work will protect ground water quality and improve maintenance efficiency. Pedestrians should expect detours to be signed where sidewalks are disrupted. Use alternate routes when possible. Project is weather dependent and is expected to be completed no later than August 15th, 2022.

 

Gilham Road at Creekside Way – Crews will be on site working on excavating and installing storm sewer pipe on Creekside Way from Gilham Rd towards Sterling Woods Dr. and on Gilham Rd. from Mirror Pond Way to Heather Grove Ln. Expect road closures and limited on-street parking and driveway access. Use alternate routes when possible. 

 

City of Springfield

Marcola Rd between 19th St & 28th St - Springfield Utility Board - Water Division is installing a 24” water main along Marcola Rd between 19th St and 28th St. Work will take place between 7am and 5pm. Expect traffic control, delays and lane closures during this time.

Lane County:
Coburg


Chipseal surface treatments will be applied on the following roads Monday through Thursday. Traffic will be controlled by flaggers. Expect delays and seek alternate routes whenever possible.

Coburg Road MP 7.40 – 12.88 (N. Coburg to Linn County)
Coburg Bottom Loop & Y Intersections MP 0.00 – 2.90 (Entire Road)
Funke Road MP 0.00 – 0.69 (Coburg Bottom Lp to End County Maintenance)
Lanes Turn Road MP 0.00 – 0.33 (Coburg Rd to End County Maintenance)

Powerline Road & Y Intersection MP 0.00 – 2.60 (Entire Road to Linn County)

Stallings Lane MP 0.00 – 0.82 (Entire Road)


See all current ODOT Projects happening in Eugene.