Road Work Advisories

Check tripcheck.com for road construction updates

About Our Advisories

Online resources for up-to-date information about City of Eugene transportation system road construction. Read below for the weekly roadwork report and follow the link at the bottom of the page or visit TripCheck for regional roadwork information.


Current City of Eugene Roadwork Advisories

Updated July 3, 2020


WORK IN PROGRESS, FOR WEEK OF 07/05/2020:

Major road construction is scheduled for the week of July 05, weather permitting. Use caution in work zones and obey traffic control signage and flaggers. Links to additional project information can be found at www.eugene-or.gov/roadwork. For real-time traffic impacts, go to TripCheck.com or twitter.com/EugenePW.



City of Eugene


13th Avenue (Lincoln St. to Alder St.): The contractor is working on sidewalk ramps, storm sewer, and traffic signals on the north side of 13th Avenue from Lincoln Street to Alder Street. Contractor is also working on portions of the curb separator for the protected cycle track. Driveways will be temporarily closed while placing the concrete, but the contractor will help the public get to where they need to go. Once complete there will be steel plates to drive over while the concrete cures. The north travel lane and parking lane is closed to vehicles, look for signs and cones. Existing traffic signals are removed, use the temporary traffic signals. Cyclists are detoured off 13th Avenue to 12th Avenue. Cyclists heading to and from the University of Oregon should use the temporary two-way cycle track on the west side of Hilyard Street to get from 12th Avenue to 13th Avenue. Cyclists can also detour onto 14th Avenue between Patterson Street and Alder Street. The temporary cycle track is protected by plastic barriers and cyclists should use the temporary traffic signals to cross Hilyard Street.


East 19th Avenue (Hilyard St. to Agate St.): All the contract work is completed.  The contractor may be working on minor repairs and cleaning up the site.  Traffic impacts should be minimal.  Watch for workers and equipment in roadway.


Roosevelt Boulevard (Hwy 99 to N. Garfield St.): Wastewater rehab work will be underway on and south of Roosevelt Boulevard between Foch Street and North Garfield Street. Work will continue Monday through Friday between the hours of 7 AM and 5 PM. Expect brief delays, lane closures, flaggers, and trucks in the roadway.


Safe Routes To School (Various Locations): Construction is complete at Barger Drive and Altimont Street. Construction of ADA will continue at the intersection of Willamette Street and West 34th Avenue. Construction of ADA ramps and a pedestrian island will commence at the intersection of Garfield Street and West 14th Avenue. Electrical boring activities will occur near the intersections of Chambers Street & West 14th Avenue and Fern Ridge Path. Traffic speeds will be temporarily reduced to 20 MPH during construction along Willamette Street and Garfield Street. Expect traffic flaggers, temporary pedestrian detours, and bikes merging with travel lanes. Expect intermittent lane closures and watch for construction crews and equipment entering and leaving the roadway. Expect delays.


Sundance Street: Additional storm sewer installation will be starting on Monday, July 6, 2020. Single lanes and driveways may be temporary closed for work. Sidewalk closures and pedestrian detours will be in place to assist foot traffic through the work zone. Parking on Sundance Street will be limited, seek alternate parking on Sundial Road and walk to your residence if possible. Watch for construction workers, trucks, and equipment in the street and surrounding area.


West 7th Ave and Washington: Starting July 7, contractors will be repairing the intersection starting at 9 p.m. There will be lane closures on both West 7th Avenue and Washington Streets. Expect delays. The work is expected to be completed by 2 a.m.


Eugene Water & Electric Board

 

Chambers Street (W. 11th Ave. to W. 13th Ave.): Chambers Street southbound lane will be closed between West 11th Avenue and West 13th Avenue during a water main replacement project. The project is being completed ahead of a planned City of Eugene street upgrade. Flaggers will control traffic. Drivers and cyclists on southbound Chambers Street in this area are advised to find alternate routes to avoid delays. Work will take place 7 AM to 5 PM Monday through Thursday.


East 8th Avenue: On Monday, July 6, a Eugene Water & Electric Board contractor will begin installing a new water transmission pipe at the intersection East Eighth Avenue and Hilyard Street. The new 36-inch pipe will be bored underneath Hilyard Street and the railroad tracks in this area to replace two approximately 100-year-old pipes. The project requires the construction of a bore pit and the closure of a portion of East Eighth Avenue where it intersects with Hilyard. Adjacent sidewalks on East Eighth will also be closed during the work.The closure of the portion of East Eighth and the adjoining sidewalks will remain in effect 24 hours a day, seven days a week through August 6. All pedestrian, bicycle and vehicle traffic will be prohibited from entering or passing through the work zone.


Oregon Department of Transportation

Interstate 105 (Delta Highway interchange to downtown Eugene at Washington-Jefferson bridge)

Bridge work is occurring. Traffic has been moved to the westbound side and will remain single lane in both directions while the work progresses. The eastbound lanes on the Willamette River Bridge are currently closed for construction. The Delta Highway ramps are open. Use caution. Expect minor delays.


Beltline/Delta Interchange Project

Beginning July 8, northbound Delta Highway travelers will take a left-turn detour to access eastbound Beltline Highway. The detour is scheduled to last for six weeks as upgrades and improvements are done to the current regular ramp.


Northbound Delta Highway will have a temporary turn lane to enter the southwest ramp to access eastbound Beltline Highway, but there will not be a light. Southbound Delta Highway travelers will see signs warning of the traffic change.


Be especially cautious in the area as people get used to the change.

Work is scheduled to be completed in mid-August.


The Beltline Highway/Delta Highway Interchange is being updated to improve safety by eliminating weaving and merging issues. Most work impacting traffic is done at night and on weekends.


For more information on the project, go to Oregon Department of Transportation’s website


City of Eugene’s cameras on Sixth and Seventh avenues now are available on tripcheck.com so motorists can check traffic conditions in real time. For more detailed project information, visit ODOT I-105 Project.


See all current ODOT Projects happening in Eugene.